Job Dependencies

Scheduled jobs can declare that they depend on other scheduled jobs. The cron runner uses those declarations to compute a topological execution order so a job never runs before the jobs it depends on. Dependencies are a scheduling-order concept: they are resolved within a single jobs:cronjob:run invocation, by Daycry\Jobs\Cron\Scheduler.

This page covers how to declare dependencies, how the ordering is computed, and the failure modes (unknown dependencies and cycles). For the broader scheduler, see Scheduling; for the configuration entry point, see Configuration.

Declaring a dependency

Use dependsOn() on the JobBuilder. It accepts either a variadic list of names or a single array, and each name must match the named() value of another registered job:

use Daycry\Jobs\Cron\Scheduler;

public function init(Scheduler $scheduler): void
{
    $scheduler->define('command', 'app:generate-report')
        ->named('generate-report')
        ->dailyAt('02:00');

    $scheduler->define('command', 'app:send-report')
        ->named('send-report')
        ->dailyAt('02:00')
        ->dependsOn('generate-report');

    // Variadic or array form both work:
    $scheduler->define('command', 'app:archive-report')
        ->named('archive-report')
        ->dailyAt('02:00')
        ->dependsOn('generate-report', 'send-report');
        // equivalently: ->dependsOn(['generate-report', 'send-report'])
}

Note: dependsOn() references jobs by their name. Always give dependent jobs an explicit named() so the relationship is stable. A job without a name falls back to a synthetic key derived from its handler and payload hash, which is awkward to reference.

How the order is computed

Scheduler::getExecutionOrder() builds a dependency graph from every registered definition and performs a Kahn topological sort by in-degree:

  1. Index every definition by its resolved name.
  2. For each dependsOn entry, add an edge dependency -> dependent and increment the dependent's in-degree.
  3. Seed a work queue with all nodes of in-degree 0 (no dependencies).
  4. Repeatedly pop a node, append it to the order, and decrement each neighbour's in-degree; when a neighbour reaches 0 it is enqueued.

The result is a list where every job appears after all of its dependencies. CronRunner then walks that list and, for each due/enabled job, either enqueues it (if it declares a queue()) or runs it inline.

// Resolved order for the example above:
// 1. generate-report   (in-degree 0)
// 2. send-report       (depends on generate-report)
// 3. archive-report    (depends on generate-report + send-report)

Note: Dependencies define order, not conditional execution. The current runner sorts the due jobs topologically and runs each one; it does not skip a dependent because its dependency was not due this minute, nor does it abort the chain if a dependency fails at runtime. Model hard "run B only if A succeeded" gating inside your handlers (e.g. have A enqueue B on success), or keep dependent jobs on the same schedule so they run together in order.

Unknown dependencies

If a job depends on a name that is not registered, getExecutionOrder() throws immediately:

$scheduler->define('command', 'app:send-report')
    ->named('send-report')
    ->dependsOn('does-not-exist'); // <-- not registered

// RuntimeException: Dependency 'does-not-exist' for job 'send-report' does not exist.

This is a fail-fast guard: a typo in a dependency name surfaces as an exception the first time the cron runner evaluates the schedule, rather than silently running in the wrong order.

Cycle detection

A circular dependency cannot be ordered. After the topological sort, the scheduler checks that every node was emitted; if not, a cycle exists and it throws:

$scheduler->define('command', 'a')->named('a')->dependsOn('b');
$scheduler->define('command', 'b')->named('b')->dependsOn('a');

// RuntimeException: Circular dependency detected in jobs.

Warning: Both the unknown-dependency and cycle errors are raised from Scheduler::getExecutionOrder(), which CronRunner::run() calls every minute. A broken dependency graph therefore stops the entire cron run, not just the offending job. Validate your init() wiring (for example with a one-off jobs:cronjob:run -testTime ...) before deploying.

Combining with other features

Dependencies compose with the rest of the builder API:

$scheduler->define('command', 'app:nightly-aggregate')
    ->named('nightly-aggregate')
    ->dailyAt('01:00')
    ->singleInstance()          // never overlap with itself (see concurrency.md)
    ->environments('production');

$scheduler->define('command', 'app:publish-dashboard')
    ->named('publish-dashboard')
    ->dailyAt('01:00')
    ->queue('reports')          // enqueued instead of inline
    ->maxRetries(3)
    ->dependsOn('nightly-aggregate');

See Concurrency & Resilience for singleInstance(), Retries for maxRetries(), and Scheduling for the frequency helpers.